Waterproofing
Concrete Repair

PLAZA DECK REHABILITATION AND BELOW-GRADE WATERPROOFING REPAIR

Full plaza deck rehabilitation and below-grade waterproofing repair at a mixed-use commercial property in Northeast Ohio, resolving chronic leaks, structural slab deterioration, and failing pedestrian coatings over occupied retail space.
PLAZA DECK REHABILITATION AND BELOW-GRADE WATERPROOFING REPAIR

PROJECT OVERVIEW

This project involved the restoration of a 30,000-square-foot elevated plaza deck constructed above occupied retail space at a mixed-use development in Northeast Ohio.

The plaza serves as a pedestrian gathering area with planters, pavers, seating walls, and decorative concrete features. Over time, tenants below began reporting persistent water infiltration, ceiling staining, and localized falling debris from deteriorated concrete.

Previous patching and coating attempts had failed to stop the leaks. The owner required a comprehensive solution that would eliminate water intrusion, restore structural integrity, and return the plaza to safe public use.

INVESTIGATION AND DIAGNOSIS

The project began with a phased exploratory investigation.

Pavers and topping slabs were selectively removed to expose the structural concrete deck. Moisture mapping, sounding, and chloride testing were performed to evaluate the condition of the slab and reinforcing steel.

Findings included:

  • Failed waterproofing membrane with widespread breaches
  • Saturated topping slabs trapping moisture against the structural deck
  • Delaminated and spalled structural concrete
  • Corroded reinforcing steel at planter perimeters and drain locations
  • Inadequate slope to drains, resulting in chronic ponding

Sealant joints at wall transitions and penetrations had also deteriorated, allowing water to bypass surface protections and migrate directly into the slab system.

The investigation confirmed that isolated repairs would not resolve the systemic moisture issues.

CHALLENGES AND CONDITIONS

Occupied Retail Below
Retail tenants remained fully operational throughout the project. Water diversion and debris protection systems were required at all times.

Complex Assembly
The plaza deck included multiple elevation changes, planters, railings, and embedded utilities. Demolition required careful sequencing to avoid damage to structural components and adjacent façade elements.

Moisture Saturation
The deck contained significant trapped moisture, requiring drying time and substrate testing prior to installing new waterproofing systems.

Drainage Deficiencies
Improper slope and undersized drains contributed to long-term performance failures and required corrective design modifications.

REPAIR STRATEGY AND APPROACH

The rehabilitation focused on correcting both structural damage and underlying water management deficiencies.

Structural Concrete Restoration
All unsound concrete was removed to expose deteriorated reinforcement. Corroded reinforcing steel was cleaned, supplemented where required, and protected prior to placement of high-performance repair mortars.

Deck Reprofiling and Drainage Correction
The deck was re-sloped using a lightweight fill system to promote positive drainage to new and existing drain assemblies. Drain bodies were replaced or modified to integrate with the new waterproofing system.

Below-Grade Waterproofing Installation
A fully adhered, reinforced waterproofing membrane system was installed across the structural slab, integrated at vertical transitions, penetrations, and drains. Terminations were carefully detailed to prevent future water migration.

Pedestrian Coating and Overlay System
A durable pedestrian traffic coating system was applied in exposed walking areas, providing slip resistance and long-term surface protection.

Sealant and Joint Replacement
All control joints, wall transitions, and penetrations were resealed using compatible, movement-capable sealants to complete the envelope.

Substrate preparation, moisture testing, and manufacturer-aligned installation procedures were strictly followed to ensure long-term performance.

EXECUTION AND LOGISTICS

The project was executed in phases over five months during late spring and summer.

Work areas were segmented to maintain partial pedestrian access and limit disruption to retail tenants below. Temporary waterproof coverings were installed at the end of each workday to prevent active leaks during construction.

Coordination between field crews, property management, and tenants was ongoing, particularly during demolition and drain replacement operations.

Daily inspections ensured that membrane terminations and transitions were properly installed before subsequent layers were applied.

RESULTS AND OUTCOMES

The completed rehabilitation:

  • Eliminated chronic water infiltration into retail spaces
  • Restored structural integrity to deteriorated slab areas
  • Corrected drainage deficiencies contributing to long-term damage
  • Installed a fully integrated waterproofing and pedestrian coating system
  • Extended the service life of the plaza deck by an estimated 20+ years

The plaza was returned to full public use with improved safety, durability, and long-term performance.

LESSONS LEARNED

Waterproofing failures are often systemic
Surface-level leaks frequently indicate broader membrane and drainage deficiencies.

Drainage drives durability
Proper slope and functional drains are essential to long-term plaza performance.

Moisture testing cannot be skipped
Installing waterproofing over saturated substrates compromises adhesion and longevity.

Integration is critical
Membranes, coatings, joints, and drains must function as a unified system — not as independent components.

© 2026 ACS RESTORATION. ALL RIGHTS RESERVED